Data's other 2026 goals are project deliverables (HA architecture, AI-augmented compliance, data platform documentation) tracked through Jira initiatives, not through the metrics warehouse.
| Date | Project | Version |
|---|---|---|
| 2 Mar | data-platform-ci | v0.1.0 |
| 6 Mar | data-platform-ci | v0.1.1 |
| 6 Mar | data-platform-ci | v0.2.0 |
Creep ratio dropped from 34.1% to 9.1%, the largest single-PI reduction the team has recorded in the trend window. Delivery against capacity rose to 104% (velocity 113 against capacity 108.4). Sprint goal hit rate was 86% (6 of 7 goals). Merged MRs grew from 53 to 277.
At the sprint level, sprints 1 to 5 each delivered roughly 75-100% of sprint capacity. Sprint 6 (IP) was a closeout with near-zero commitment.
Bug count of 10 is flat vs PI 8 and roughly double the PI 5-7 range (1-12). Volume is still low relative to commitment.
The 50.5% completion against commitment reflects a commitment that was 186% of measured capacity. The delivery-against-capacity number (104%) is the more honest read of throughput.