Engineering Performance · PI 9 Brief

Fusion

February 5 – April 28, 2026 · Sprints 1–6
Fusion closed PI 9 with every sprint goal hit — 18 of 18 across all six sprints — and total resolved work at 108% of capacity (119 points of velocity against 110.1 of capacity). Committed Done rose to 100.5 points from 67 in PI 8, creep ratio dropped by more than half to 23.4%, completed bugs fell from 12 to 5, and merged MRs doubled to 104.
Completion Ratio
48.6%
▲ +10.1pp vs PI 8
target ≥ 80%
Committed Done vs Capacity
91.3%
▲ +31.3pp vs PI 8
100.5 / 110.1 pts
Velocity vs Capacity
108.1%
▲ +9.6pp vs PI 8
119 / 110.1 pts
Sprint Goals Hit
100%
18 / 18 · no PI 8 data
target ≥ 80%
Creep Ratio
23.4%
▼ −24.9pp vs PI 8
target ≤ 20%
Bugs Completed
5
▼ −7 vs PI 8
Bug + Anomaly issues
MRs Merged
104
▲ +53 vs PI 8
110 opened

Capacity, Commitment & Velocity — PI 5 → PI 9

PI 9 Sprint-level Capacity, Commitment & Velocity

Creep Ratio — PI 5 → PI 9

Bugs Completed — PI 5 → PI 9

Goal Progress

GoalTargetPI 9Status
Sprint and PI goal achievement (shared, all Team Leads) ≥ 80% 100% (18/18) Pass

No Fusion-specific engineering metric goals for 2026 are tracked via the warehouse; only the shared sprint-goal achievement target applies. See the engineering goals doc for any project-deliverable goals.

What stood out

Fusion hit 18 of 18 sprint goal checkboxes across PI 9 — a 100% goal hit rate, and the first PI in the trend window with parseable goal data for the team. Goals spanned the CTRT-Ocoro frontend and backend work, the n8n use cases, xCures authentication and spikes, and the EVO2 Peak data page.

Total resolved work exceeded capacity: velocity landed at 119 points against 110.1 of capacity (108.1%), and Committed Done alone reached 91.3% of capacity — up from 60.0% in PI 8. Committed Done of 100.5 points is the team's highest since PI 6 (113.5).

Creep ratio fell to 23.4% from 48.3% in PI 8, with sprints 3–6 all at or below 15.2%. Completed bugs dropped from 12 to 5, and merge request throughput roughly doubled: 104 merged and 110 opened, versus 51 and 59 in PI 8.

Where the data is mixed

Completion ratio was 48.6%, below the 80% org target, though up 10.1pp from PI 8. The gap sits in planning volume rather than output: commitment totaled 207 points against 110.1 of capacity — every sprint committed above its capacity, with sprint 6 committing 37 points against a capacity of 9. No individual sprint exceeded a 64.3% completion ratio.

Creep ratio at 23.4% remains above the 20% ceiling, driven by the first two sprints (50% and 61.3%); of 48.5 creep points added, 18.5 were completed (38% creep-done ratio). Sprint 2 in particular completed 1 of 19 creep points added.

Deployment and lead time tracking are not yet configured for Fusion — the team's only registered environment is dev, with no production or staging tier — so DORA metrics are omitted from this brief.